Road Work Ahead

Update 7/17/2026:

Below is the updated schedule (07/17/2026) weather dependent:

Haines Paving & Landscaping Inc. is the contractor responsible for the road repair contract and then AMS will be the contractor responsible for the oil and chip and slurry seal.

  • Monday, July 20th-22nd Thompson Mill Road- work will take place near where the culvert was replaced last year.
  • Thursday, July 23rd- the following week of July 27th- Mud Road Crossover Pipe- It will take up to 4 days, and the road will be closed from 7AM-7PM during work (local access will be maintained). Mud Road will be close from Penns Park Road up to 560 Mud Road. Anyone who needs to access 560 Mud Road or beyond that point should access Mud Road from Worthington Mill Road.
  • Monday, August 3rd (maybe earlier if the Mud Road Project is completed early)- Hallowell, Wooley and Crescent Drive Mill and Paving is tentatively scheduled but depends on the completion of the projects above. No parking will be allowed on the roadway during this time- homeowners will be notified once the date is set.
  • Monday, July 27th (weather dependent) Oil and Chip will take place on the following roadways:
    • Thompson Mill Road- Oil and Chip
    • Mud Road- Oil and Chip
    • Fox Hill Drive- Oil and Chip/Slurry Seal
    • Martindell Drive- Oil and Chip/Slurry Seal

 Update 7/8/2026:

Weather-permitting, Haines will mill out the base repairs on Lark and Pheasant on Thursday 7/9, and the area will be paved the following week during the Thompson Mill Road project.

Update 07/01/2026:

Below is the updated schedule:

Haines Paving & Landscaping Inc. is the contractor responsible for the road repair contract and then AMS will be the contractor responsible for the oil and chip and slurry seal.

  • Monday, June 29th-July 10th Wrightstown Hunt (Fox Hill Drive and Martindell Drive)- work on base repair, inlets, and Belgian Blocks will take place this week. This should be completed by July 8th (weather dependent). No work will take place on July 3rd or July 6th due to the holiday.   
  • Monday, July 13th-17th Thompson Mill Road- work will take place near where the culvert was replaced last year. Also, a small area of base repair will take place on Lark and Pheasant this week (probably take 2-3 days).
  • Monday, July 20th-24th Mud Road Crossover Pipe- It will take up to 4 days, and the road will be closed from 7AM-7PM during work (local access will be maintained). Mud Road will be close from Penns Park Road up to 560 Mud Road. Anyone who needs to access 560 Mud Road or beyond that point should access Mud Road from Worthington Mill Road.
  • Monday, July 27th- Hallowell, Wooley and Crescent Drive Mill and Paving is tentatively scheduled but depends on the completion of the projects above. No parking will be allowed on the roadway during this time- homeowners will be notified once the date is set.
  • End of July (tentative dates coming soon!)- Oil and Chip will take place on the following roadways:
    • Thompson Mill Road- Oil and Chip
    • Mud Road- Oil and Chip
    • Fox Hill Drive- Oil and Chip/Slurry Seal
    • Martindell Drive- Oil and Chip/Slurry Seal

Please note some temporary closures or delays may happen during construction. Please be patient and be careful around the crews when they are working.

Update 06/24/2026:

Please note that there is a delay for some of the supplies for the Mud Road Project so that will be delayed a week-On Monday, June 29th- the contractor will start in Wrightstown Hunt for the inlets and Belgian block repair.  Please keep checking here and on our social media accounts for any updates.  

2026 Road Program Schedule

Here is the tentative schedule which will be updated as needed depending on weather or anything that could arise that could affect the work:

Haines Paving & Landscaping Inc. is the contractor responsible for the road repair contract and then AMS will be the contractor responsible for the oil and chip and slurry seal.

  • Monday, June 29th- Wrightstown Hunt (Fox Hill Drive and Martindell Drive)- work on base repair, inlets, and Belgian Blocks will take place this week.
  • Tuesday, July 7th- Mud Road Crossover Pipe- It will take up to 4 days, and the road will be closed from 7AM-7PM during work (local access will be maintained). Mud Road will be close from Penns Park Road up to 560 Mud Road. Anyone who needs to access 560 Mud Road or beyond that point should access Mud Road from Worthington Mill Road.
  • Tuesday, July 13th- Thompson Mill Road- work will take place near where the culvert was replaced last year. Also, a small area of base repair will take place on Lark and Pheasant this week.
  • Monday, July 20th- Hallowell, Wooley and Crescent Drive Mill and Paving is tentatively scheduled. No parking will be allowed on the roadway during this time- homeowners will be notified.
  • End of July (tentative dates coming soon!)- Oil and Chip will take place on the following roadways:
    • Thompson Mill Road- Oil and Chip
    • Mud Road- Oil and Chip
    • Fox Hill Drive- Oil and Chip/Slurry Seal
    • Martindell Drive- Oil and Chip/Slurry Seal

Please note some temporary closures or delays may happen during construction. Please be patient and be careful around the crews when they are working.